Sun Feb 08 14:40:29 UTC 2026: # Idukki Construction Freeze: New Restrictions Imposed Following High Court Order
The Story: A recent letter from the Local Self-Government Department (LSGD) Joint Director in Idukki has effectively halted construction permits across 13 panchayats in the district. This action mandates that all panchayats require a No Objection Certificate (NOC) from the Revenue Department before issuing any construction permits. This stringent measure follows a 2010 High Court order and earlier restrictions imposed in July 2023 and confirmed in July 2024, classifying these areas as “red zones” based on a scientific study.
Key Points:
- The LSGD letter was issued on February 6, 2026.
- 13 panchayats are affected: Chinnakkanal, Munnar, Pallivasal, Vellathooval, Devikulam, Bison Valley, Santhanpara, Udumbanchola, Mankulam, Marayur, Kanthallur, Edamalakkudy, and Vattavada.
- A 2010 High Court order mandates a Revenue Department NOC for construction activities in eight villages across Devikulam and Udumbanchola.
- The restrictions apply to all construction, including temporary sheds, residential buildings, commercial establishments, and LIFE Mission Project buildings.
- Former Idukki District Collector Sheeba George confirmed restrictions under the District Disaster Management Authority (DDMA) Act in July 2024.
Key Takeaways:
- Construction activities in Idukki’s ecologically sensitive zones are now heavily regulated.
- The Revenue Department’s role in approving construction projects in these areas has significantly increased.
- The new restrictions may impact ongoing construction and future development, including government-sponsored housing projects like the LIFE Mission.
- The enforcement of the 2010 High Court order is being rigorously implemented now, indicating a renewed focus on environmental protection.