Fri Jan 16 18:07:39 UTC 2026: ### Kerala High Court Rejects Kochi Corporation’s Plea to Extend Eviction Deadline
The Story:
The Kerala High Court has denied a request from the Kochi Corporation to extend the deadline for evicting encroachers from ‘poramboke’ land (government-owned land often bordering water bodies) near the Konthuruthy river. The court’s original order, issued on December 16, 2025, mandated the civic body and the Revenue department to complete the evictions within four months and to ensure the rehabilitation of those affected. The situation involves 126 families currently residing on the encroached land, and the Konthuruthy Action Council is seeking clarity on rehabilitation and compensation plans.
Key Points:
- The Kerala High Court rejected the Kochi Corporation’s request for an extension to evict encroachers.
- The court previously ordered evictions to be completed within four months, starting December 16, 2025.
- 126 families are affected by the eviction order.
- The Kochi Corporation had formed a committee to represent the affected families’ interests.
- The Konthuruthy Action Council is demanding clarity on rehabilitation and compensation measures.
Key Takeaways:
- The Kerala High Court is taking a firm stance on enforcing eviction orders related to encroached ‘poramboke’ land.
- The lack of clarity on rehabilitation and compensation is causing resistance and uncertainty among the affected families.
- The Kochi Corporation faces significant challenges in balancing legal mandates with the welfare of its residents.